How to Calculate Concrete for a Slab, Footing, or Column
Ordering concrete is expensive and unforgiving — short one yard and you're stuck with a cold joint; order too much and you pay for what goes in the dumpster. Here's how pros calculate concrete for slabs, footings, and columns without guessing.
The core formula
Every concrete calculation — slab, footing, column, or stair — is just volume math. The formula is the same:
The divisor is 27 because one cubic yard equals 27 cubic feet (3 ft × 3 ft × 3 ft). From there, the only difference between shapes is how you measure them.
Step-by-step for a concrete slab
Measure length, width, and thickness in feet
Convert inches to feet by dividing by 12. A 4-inch slab is 0.333 ft thick. A 6-inch slab is 0.5 ft. This is the step most DIYers get wrong — plugging inches into a cubic-yard formula gives results that are 1,728× too large.
Multiply to get cubic feet
For a 20 ft × 30 ft × 4 in slab: 20 × 30 × 0.333 = 200 cubic feet.
Divide by 27 to get cubic yards
200 ÷ 27 = 7.41 cubic yards. This is the raw concrete needed, before waste.
Add waste factor (5–10%)
Spillage, over-excavation, uneven subgrade, and form bulging eat concrete. Industry standard is 5% for slabs with rigid forms and 10% for footings or rough subgrade. For the slab above: 7.41 × 1.05 = 7.78 cubic yards — order 8 yards (most plants sell in 0.25 yard increments, but you rarely want to cut it that close).
Convert to bags (only for pours under 1 yard)
If you're mixing from pre-mix bags instead of calling a ready-mix truck:
- 1 cubic yard ≈ 45 × 80 lb bags (Quikrete, Sakrete)
- 1 cubic yard ≈ 60 × 60 lb bags
- 1 cubic yard ≈ 90 × 40 lb bags
Above 1 cubic yard, bags become both more expensive and more labor-intensive than ready-mix delivery.
Footings
A footing is just a long, narrow slab. Same formula: Length × Width × Depth ÷ 27. A 30 ft continuous footing, 18 inches wide and 12 inches deep, works out to 30 × 1.5 × 1 = 45 cubic feet = 1.67 cubic yards. Add 10% waste for dug trenches: 1.84 cubic yards.
For stepped footings, calculate each step separately and sum.
Columns and piers
Round columns use the cylinder formula:
A 10-inch diameter column, 8 feet tall: radius = 0.417 ft, so π × 0.417² × 8 = 4.37 cubic feet = 0.162 cubic yards. Add 10% waste: 0.178 cubic yards. Below 0.25 cubic yards, use bags.
Stairs
Stairs are the ugliest calc in the book because every step is a wedge. The shortcut:
- Calculate the triangular side area: ½ × total rise × total run
- Multiply by stair width
- Divide by 27
This gives the minimum volume (the wedge under the steps). For cast-in-place stairs, add 20% to account for the actual tread/riser geometry that sits above the wedge.
Common mistakes
- Using inches in the formula. Cubic yards requires all dimensions in feet.
- Forgetting waste factor. Your slab will always need 5–10% more than the geometric volume. Concrete doesn't "stretch."
- Rounding down. Never round down when ordering. If the math says 7.41 yards, don't order 7 — you'll be paying an emergency short-load fee when the truck runs out before the pour finishes.
- Ignoring slab reinforcement volume. Rebar and welded wire mesh take up negligible volume, so you can ignore them. Post-tension cables similarly. But if you have large drain pockets, subtract their volume.
Skip the math — use the calculator
BuildCalc Pro's concrete calculator handles slabs, footings, columns, and stairs automatically, including bag counts and waste factor. Free to use, no signup required.
Open Concrete Calculator →